Question: Callers are helped in a process with two sequential resources. A worker in the first resource helps 0 . 7 callers per minute and a

Callers are helped in a process with two sequential resources. A worker in the first resource helps 0.7 callers per minute and a worker in the second resource helps 4.3 callers per minute. The first resource has 4 workers and the second resource has 1 worker.
What is the capacity of this process in terms of callers per minute?
Note: Round your answer to 2 decimal places.