Question: Cameron is overseeing a project for his summer internship. Although it is a simple task, he is preparing a scheduling tool to help him manage

Cameron is overseeing a project for his summer internship. Although it is a simple task, he is preparing a scheduling tool to help him manage the project. More specifically, he writes out the objective and lists the sequence of activities that need to transpire to meet the objective. He also notes when each activity will start and end, and who will complete each activity. Considering this scenario, Cameron is likely using a: Group of answer choices SWOT analysis. Gantt chart. planning sheet. balanced scorecard