Question: can I have help with this question #13 OPS 1100 E Test: E-Test3 Assume that activity G has the following times: Early start time =
can I have help with this question #13

OPS 1100 E Test: E-Test3 Assume that activity G has the following times: Early start time = 7 days Early finish time = 13 days Late start time = 15 days Late finish time = 21 days Which of the following statements is TRUE about activity G? A. Activity G is on the critical path. O B. Activity G has a slack time of 8 days. O C. Activity G takes 14 days to complete. O D. Activity G takes 2 days to complete
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
