OPS 1100 E Test: E-Test3 Assume that activity G has the following times: Early start time = 7 days Early finish time = 13 days Late start time = 15 days Late finish time = 21 days Which of the following statements is TRUE about activity G? A. Activity G is on the critical path. O B. Activity G has a slack time of 8 days. O C. Activity G takes 14 days to complete. O D. Activity G takes 2 days to complete