Question: can i have help with this question Im not sure i got it right ULUT This lest: 39 pts possible B D A 2 O

can i have help with this question Im not sure i got it right
can i have help with this question Im not sure i got
it right ULUT This lest: 39 pts possible B D A 2

ULUT This lest: 39 pts possible B D A 2 O + E 3 C 3 F Earliest Finish Slack Activity Time 2 1 3 Activity A B D 1 Latest Start 0 3 2 4 Earliest Start 0 2 2 3 5 5 11 0 Latest Finish 2 4 5 11 11 11 15 7 mo 5 10 8 11 15 3 3 0 F 5 11 0 4 3 C D E F G NINO 3 4 11 Using the information shown in the table above, what is the project duration? O A 14 O B. 12 e c. 15 D. 10 O Type here to search