Question: can some one answer it please as soon as possible Activity Predecessor Duration(s) im dry B D E F G H I J 8 9
can some one answer it please as soon as possible
Activity Predecessor Duration(s) im dry B D E F G H I J 8 9 6 A A B B D.F E F GIH 4 8 5 Based on the precedence table above: 1. Determine the critical path for this project. (3 Marks) 2. Determine the total float for this project (2 Marks) 3. Assuming the project starts on 31 May 2020 (Sunday) and the team take a compulsory day off on Saturday, determine the (3 Marks) a) Early finish for activity B b) Late start for activity E c) Late start for activity C MAY 2020 1 2. 9 8 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31