Question: can some one help me to solve this problem thanks. The following diagram describes a process that consists of eight separate operations, with sequential relationships
can some one help me to solve this problem thanks.

The following diagram describes a process that consists of eight separate operations, with sequential relationships and capacities (units per hour) as shown below. Operation Operation Operation A B C Operation Operation G H Operation Operation Operation D E F Capacity: Operation A: 15/hr Operation B: 10/hr Operation C: 19/hr Operation D: 3/hr Operation E: 8/hr Operation F: 12/hr Operation G: 28/hr Operation H: 22/hr . What is the current hourly capacity of the entire process