Relevant information for a project consisting of activities A, B,... H is provided in the table below and the project network is provided. Activity Immediate Predecessors Time in weeks N/A 3 09 B 3 6 D B, C 7 m C 7 F B 5 G DE 7 H F G 7 What is the earliest start time for activity G? Answer 20