Question: Can someone help me with this question, please. Item: RST Description: Lot Size: 100 units Lead Time: 3 weeks Date 1 2 3 4 5

Can someone help me with this question, please.

Can someone help me with this question, please.

Item: RST Description: Lot Size: 100 units Lead Time: 3 weeks Date 1 2 3 4 5 8 Gross requirements 20 60 100 80 60 Scheduled receipts 100 Projected on hand 80 Planned receipts Planned order releases The Date indicates the week numbers (1 to 8). The cells indicate quantities in Units. Complete the MRP record fill all the cells for projected on hand, planned receipts and planned order releases