Question: Question 8 2 pts Table 16.5 Use the information in Table 16.5. ITEM: RST Description: Lot Size 100 units Lead Time: 3 weeks 2 .

Question 8 2 pts Table 16.5 Use the information

Question 8 2 pts Table 16.5 Use the information in Table 16.5. ITEM: RST Description: Lot Size 100 units Lead Time: 3 weeks 2 . 1 2 3 4 5 6 7 8 Date Gross requirements 20 60 100 80 60 Scheduled receipts 100 Projected on Hand 80 Planned receipts Planned order releases Which one of the statements concerning item RST is TRUE? There are exactly two planned order releases needed for the first 8 weeks. The planned order release in week 2 is for 100 units. The first planned receipt occurs in week 5. The planned receipt in week 7 is 80 units