Question: can someone please explain these problems to me please, thank you! The following activities are part of a project to be scheduled using CPM: o.



The following activities are part of a project to be scheduled using CPM: o. What is the critical path? A-B-E-GA-C-D-F-GA-C-D-E-GA.B-D-F-G b. How many weeks will it take to complete the project? c. How much slack does activity B have? Schedule the following activities using CPM: b. What is the critical path? A-B-D-F-G-H A-B-D-E-H A-C-E.F-G-H A.C-E-H c. How many weeks will it take to complete the project? c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B. 1 week: H.2 weeks: F,4 weeks. C. 5 weeksi F, 2 weeks: G, 2 weeks. A. 2 weeks: C. 3 weeks: F,1 week