Question: Can someone please explain what would would be the new assignment and project duration and if the project can be completed in less time Consider


Can someone please explain what would would be the new assignment and project duration and if the project can be completed in less time
Consider a project with the activity precedence relationships and time estimates given in the following table. Two workers are available. Due to his skill set, Jack is responsible for activities A and B. Similarly, only Amy can do activities C, D and E. (c) Assume Jack and Amy can be cross trained to do any activity, but will not share activities. Can the activities be reassigned to Jack and Amy such that the project is completed in less time? If so, indicate the new assignment and project duration. ( 2 points)Step by Step Solution