Question: can someone please help and show work. 5.15. Using the following route information, open order information, and MRP planned orders, calculate the load on the
can someone please help and show work.
5.15. Using the following route information, open order information, and MRP planned orders, calculate the load on the work center. Routing Part 123 Part 456: Setup time = 2 standard hours Run time per piece = 3 standard hours per piece Setup time = 3 standard hours Run time per piece = 1 standard hour per piece Open Orders for parts Planned Orders for parts Week 1 2 3 1 2 2 3 3 123 12 8 5 0 5 5 10 456 15 A 5 0 10 15 1 See Capacity Management 129 Lead report Week 1 2 3 Released Load 123 456 Planned Loud 123 456 Total Load
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
