Question: someone please help and show work 5.14. A work center has the following open and planned orders for week 4. Calculate the total standard time
someone please help and show work
5.14. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load). Order Quantity Setup Time (hours) Run Time (hours/piece) Total Time (hours) Released Orders 125 200 0.50 0.10 345 70 0.75 0.05 Planned Orders 565 80 1.00 0.25 785 35 1.50 0.15 Total Time (standard hours)