Question: Can this question please be answered using the values given in this question specifically? The project information for the custom order project of the Air

Can this question please be answered using the values given in this question specifically?
The project information for the custom order project of the Air Control Company is presented here. Compute the early and late activity times and slack times. Identify the critical path. How many days will the project take? ID A B C D E - Activity Order review Order standard parts Produce standard parts Design custom parts Software development Manufacture custom hardware Assemble Test Predecessor Time None 4 A 2 A 19 A 17 A 42 C, D B, F 20 E, G 8 20 G . days. The project will take The critical activities are The late start on Activity C is The slack on Activity C is The slack on Activity D is The early start on Activity E is days. days. days. daysStep by Step Solution
There are 3 Steps involved in it