Question: Can you answer questions 3 & 4 ? 3- ABC textile mills produces a special cloth. The demand for this cloth is 10 yards per
3- ABC textile mills produces a special cloth. The demand for this cloth is 10 yards per day. The production setup (ordering) cost is $100 per order and holding cost is $.20 per week. If production nite is 600 yards per month, find; a) Compute the optimal order quantity b) Compute the production run time. c) Find maximum inventory level. d) Find the total cost c) If SS=25, find TC. 4- Given the following product structure (BOM) and inventory status. Determine the quantity and timing of each component that must be produced. Planned order for component A is 50 units in period 10