Question: can you help? 3. Using the following information, what is the probability of completing the project in 25 periods? ID Predecessor Variance [(b -- a)/6]
can you help?
3. Using the following information, what is the probability of completing the project in 25 periods? ID Predecessor Variance [(b -- a)/6] 3 7 4 2 3 4 5 6 7 8 000 UN Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release 2 None None None 1 1 4 3 2,5,6,7 NAVO NONNAW 10 10 16 3 2 1