Question: Can you help me solve this problem... Calculate the ES/EF (Forward Pass) for each of the activities above. (Activity H has already been calculated) Calculate
Can you help me solve this problem...
- Calculate the ES/EF (Forward Pass) for each of the activities above. (Activity H has already been calculated)
- Calculate the LS/LF (Backward Pass) for each of the activities above.
- Calculate the slack or float in each of the non-critical path tasks.
- What is the Critical Path?

N S U W 9 3 2 5 Y 8 P 5 K OH 5 V X Z 0 5 5 5 3 10 M R 4 5 Q 3 1. Calculate the ES/EF (Forward Pass) for each of the activities above. (Activity H has already been calculated) 2. Calculate the LS/LF (Backward Pass) for each of the activities above. 3. Calculate the slack or float in each of the non-critical path tasks. O 4. What is the Critical Path? O