Question: can you just answer question 3 please Assume the network and data that follow. compute the total direct cost for each project duration. If the

can you just answer question 3 please
can you just answer question 3 please Assume the network and data
Assume the network and data that follow. compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), and $250 (16), compute the total project cost for each duration. Plus the total direct, indirect, and project cost for each of these generations on the cost-time graph. what is the optimum cost-time schedule for the project? What is this cost?
that follow. compute the total direct cost for each project duration. If

Lap Power Donisa Oupar 1 anderat huwer Denetion is 1. Draw a project netabrk froen the following information. Activities B and H can be shortened to a minimxam of 2 weeks. Which actini) would you shorten to reduce the project duration by 2 weeks? Why? 2." Use the information contained below to compees one time unit per move using the least cost method. Reduce the schedule untit you reach the crash poing of the network. Fer each move illentify whar activity(s) was crashed the adjuupd total cost. 4. Given the data and infermatioe that follew, compute the total direst cont for tach project duration. If the ind irect cons for each project daration are 500 (15 time unito), 570(14),550(13),540(12), and 510(11), compute the total pioject cost for each duration. What is the eptimum cost stime schesule for the peojest" What is this cost? 3. Assume the netaork and data that follow. Compute the total direct cen for each peoject duration. If the indirect coss for each project duration are 5430 (19 time units). $350 (18), 5300(17), and $250 (16), compute the total preiet cov for each duration. Plot the tocal direct, indirect, and peoject costs for tach of these durations on a cost-time graph. What is the optimum cosl-time shedwle for the peoject? What is this coit? Chapter 9 Reducing Projert Dwation 3 as Lap Power Donisa Oupar 1 anderat huwer Denetion is 1. Draw a project netabrk froen the following information. Activities B and H can be shortened to a minimxam of 2 weeks. Which actini) would you shorten to reduce the project duration by 2 weeks? Why? 2." Use the information contained below to compees one time unit per move using the least cost method. Reduce the schedule untit you reach the crash poing of the network. Fer each move illentify whar activity(s) was crashed the adjuupd total cost. 4. Given the data and infermatioe that follew, compute the total direst cont for tach project duration. If the ind irect cons for each project daration are 500 (15 time unito), 570(14),550(13),540(12), and 510(11), compute the total pioject cost for each duration. What is the eptimum cost stime schesule for the peojest" What is this cost? 3. Assume the netaork and data that follow. Compute the total direct cen for each peoject duration. If the indirect coss for each project duration are 5430 (19 time units). $350 (18), 5300(17), and $250 (16), compute the total preiet cov for each duration. Plot the tocal direct, indirect, and peoject costs for tach of these durations on a cost-time graph. What is the optimum cosl-time shedwle for the peoject? What is this coit? Chapter 9 Reducing Projert Dwation 3 as

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!