Question: Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are
Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), and $250 (16), compute the total project cost for each duration. Plot the total direct, indirect, and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project? What is thiscost?
.png)
Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 50 60 70 50 100 90 50 10 100 $470 project duration 19 Total direct cost 10x
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
The optimum duration is 17 time units at a cost of 840 AC... View full answer