Question: Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are

Assume the network and data that follow. Compute the total direct cost for each project duration. If the indirect costs for each project duration are $400 (19 time units), $350 (18), $300 (17), and $250 (16), compute the total project cost for each duration. Plot the total direct, indirect, and project costs for each of these durations on a cost-time graph. What is the optimum cost-time schedule for the project? What is thiscost?

Assume the network and data that follow. Compute the total

Act. Crash Cost (Slope) Maximum Crash Time Normal Time Normal Cost 50 60 70 50 100 90 50 10 100 $470 project duration 19 Total direct cost 10x

Step by Step Solution

3.40 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The optimum duration is 17 time units at a cost of 840 AC... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1417).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!