Question: Can you please do a Budget Or Cost Baseline For the project below? Activity Description Duration Date Start Date End Direct Cost A1 Land Measurements

Can you please do a Budget Or Cost Baseline For the project below?

Activity Description Duration Date Start Date End Direct Cost
A1 Land Measurements 8 15-Jan-14 24-Jan-24 $ 2,400.00
B2 Layout of measurements stakes 12 25-Jan-24 9-Feb-24 $ 3,600.00
C3 Analysis of surrounding environment 17 25-Jan-24 16-Feb-24 $ 5,100.00
D4 Building of foundation 22 12-Feb-24 12-Mar-24 $ 6,600.00
E5 Approval of construction papers 13 19-Feb-24 6-Mar-24 $ 3,900.00
F6 Layout of building framework 15 19-Feb-24 8-Mar-24 $ 4,500.00
G7 Gas line installment 18 12-Feb-24 13-Mar-24 $ 5,400.00
H8 Electrical wiring 27 14-Mar-24 19-Apr-24 $ 8,100.00
I9 Interior Plumbing 20 7-Mar-24 3-Apr-24 $ 6,000.00
J10 Wall Construction 25 22-Apr-24 24-May-24 $ 7,500.00
K11 Insulation 23 4-Apr-24 6-May-24 $ 6,900.00
L12 Drywall 20 4-Apr-24 1-May-24 $ 6,000.00
M13 Roofing 10 27-May-24 7-Jun-24 $ 3,000.00
N14 Restaurant Construction 40 14-Mar-24 8-May-24 $ 12,000.00
O15 Swimming Pool 20 27-May-24 Jue 21, 2024 $ 6,000.00
P16 Fencing 10 27-May-24 7-Jun-24 $ 3,000.00
Q17 Telephone Lines 22 24-Jun-24 23-Jul-24 $ 6,600.00
R18 Completion of Underground -
S19 Snack Bar 20 9-May-24 5-Jun-24 $ 6,000.00
T20 Stream Building -
U21 Outside Lightning 12 10-Jun-24 25-Jun-24 $ 3,600.00
V22 Parking Lots 5 24-Jul-24 30-Jul-24 $ 1,500.00
W23 Drainage Construction 10 24-Jul-24 6-Aug-24 $ 3,000.00
X24 Safety Inspection 15 7-Aug-24 27-Aug-24 $ 4,500.00
Y25 Landscaping 24 31-Jul-24 2-Sep-24 $ 7,200.00
Z26 Final Permits/Releases 15 3-Sep-24 23-Sep-24 $ 4,500.00
TOTAL 423 $ 126,900.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!