Question: Can you solve this question? A, B D Question 2: Consider the activities, their predecessors and completion durations given below: Activities Immediate Time Predecessors (days)
Can you solve this question?
A, B D Question 2: Consider the activities, their predecessors and completion durations given below: Activities Immediate Time Predecessors (days) A 8 B 4 2 3 E D 7 F D 2 G D H F G 1 E, H 3 J H L JK 2 M L 7 4 I I 4 8 a) Draw the AON (Activity on Node) network. b) Draw the AOA (Activity on Are) network. c) Perform the critical path activities (ie, calculate Earliest start (ES), Earliest finish (EF), Latest start (LS) and Latest finish (LF) for each activity). d) Compute the slack or free time for each activity, e) Decide the critical path and state the completion time of entire project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
