Question: Can you solve this shit for me? Consider a construction project with 7 activities as shown in the table below. The predecessors of each activity
Can you solve this shit for me? Consider a construction project with 7 activities as shown in the table below. The predecessors of each activity and the duration of the activities are given. The number of cranes (consider it as a resource) required by each activity is also listed. The organization has only 6 cranes available with them.
| Construction Project Activities | |||
Activity | Predecessor(s) | Duration (in days) | # of cranes needed |
A | - | 3 | 6 |
B | A | 2 | 1 |
C | B | 5 | 5 |
D | B | 4 | 2 |
E | C | 9 | 4 |
F | C,D | 2 | 4 |
G | E,F | 1 | 6 |
Given the resource constraint (i.e., only 6 cranes are available for the project), discuss the potential over-allocation of this resource and how to resolve it - by responding to the following questions:
- Identify the days when the resource is over-allocated.
- How will you resolve the over-allocation?
- What is the new project duration?
- What is the new critical path?