Question: Can you solve this shit for me? Consider a construction project with 7 activities as shown in the table below. The predecessors of each activity

Can you solve this shit for me? Consider a construction project with 7 activities as shown in the table below. The predecessors of each activity and the duration of the activities are given. The number of cranes (consider it as a resource) required by each activity is also listed. The organization has only 6 cranes available with them.

Construction Project Activities

Activity

Predecessor(s)

Duration (in days)

# of cranes needed

A

-

3

6

B

A

2

1

C

B

5

5

D

B

4

2

E

C

9

4

F

C,D

2

4

G

E,F

1

6

Given the resource constraint (i.e., only 6 cranes are available for the project), discuss the potential over-allocation of this resource and how to resolve it - by responding to the following questions:

  1. Identify the days when the resource is over-allocated.
  2. How will you resolve the over-allocation?
  3. What is the new project duration?
  4. What is the new critical path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!