Question: CANNOT use excel Answer the following questions using the project cash flows for Project A and Project B: a. Label the graph below just luke
CANNOT use excel
Answer the following questions using the project cash flows for Project A and Project B:
a. Label the graph below just luke the class video (including axis labels) with numbers for the 2 mutually exclusive projects (below)
b. Identify which project you would choose IRR.
c. Identify which project you would choose using NPV for these discount rates: 0%, 8%, & 12%.
d. Write a brief explanation of why your NPV decision changes and at what rate. that decision begins to conflict with. the IRR choice.

NPV Project B Project Cash Flows A B -10,000 -10,000 10,000 1,000 1,000 1,000 1,000 12,000 Project A Crossover rate Discount rate (R)