Question: Carefully examine the following steps below: ABC project has been successfully delivered. John, the Project Manager is executing formal closure for ABC project. q ,

Carefully examine the following steps below:
ABC project has been successfully delivered.
John, the Project Manager is executing formal closure for ABC project.
q,
Which of the following should be Step 3?
A: John should update the bid documents.
B: John should obtain Stakeholder acceptance.
C: John should reassign the project team.
D: John should release the material and equipment resources.