Question: Carla has just completed developing a work breakdown structure with her team and has entered a sequenced task list into Project. What step should Carla
Carla has just completed developing a work breakdown structure with her team and has entered a sequenced task list into Project. What step should Carla take next? A Link the tasks. B Create a summary task for the entire project. C Determine the lead time for each task. D Set the project start date