Question: Carla is auditing Maria's project, and notes that the project's BAC is $575,000 and the CPI is 0.91. Calculate EAC for this project?
Carla is auditing Maria's project, and notes that the project's BAC is $575,000 and the CPI is 0.91. Calculate EAC for this project?
Step by Step Solution
There are 3 Steps involved in it
First we need to know the formula for EAC Estimate at Completion in ... View full answer