Question: EVA Worksheet Problem 1 Week AC PV EV CV CPI SV SPI 2 $ 7 2 , 0 0 0 A project manager is analyzing
EVA Worksheet
Problem
Week AC PV EV CV CPI SV SPI
$
A project manager is analyzing progress on a project to make a minute documentary. Its the end of week two on this three week project. The actual cost is $ They have minutes of usable film. The budgeted total cost is $ Determine PV EV CV CPI, SV and SPI.
a First, map each description to an EVA category. Then, fill in the table.
b What do the SPI and CPI values mean in this example? Explain in plain English.
c Could a project or task be where we expect in terms of cost but behind on schedule? Hint: see formulas
Problem
You are managing a project to film promotional videos to be posted on YouTube, to promote one of the UI fraternities. Your project has a BAC of $ One of the tasks on the critical path is to arrange filming locations. The task has a BAC of $ You have confirmed of the locations. The task is scheduled to take weeks days and it is the end of day You have spent $ so far.
a Identify the tasks BAC, AC EV and PV
b Calculate SPI and CPI.
c What do the results tell you about the tasks schedule and budget?
Problem
You are managing a construction project with a BAC of $ You have built of the houses, and you have just finished week on the project, out of the scheduled weeks. Your actual cost has been $ so far. Determine the estimate to complete ETC the project, and briefly explain what the result means.
Problem
You are managing a task on the critical path which has a BAC of $ The task is percent complete. The team has completed weeks on the task, and it was scheduled to take weeks. You have spent $ on the task so far. Calculate the cost performance index CPI and schedule performance index SPI Briefly explain what the results mean.
Problem
a For the following tasks, complete EV SV CV CPI, SPI, ETC and EAC. Show your work.
All costs in $ all time in days. Completion is given; note that tasks A through D should be complete at this point per the project schedule. PV BAC, and EV Complete PV for those tasks, because we should be done with the project by now. Task E has a BAC of $ Tip: Draw an AON diagram to see the relationships and timing of tasks.
Task
Complete Time days PV EV AC SV CV CPI SPI ETC EAC
A Breadboard design finalized
Predecessor: $ $
B Build breadboard mockups
Predecessor: A $ $
C Update rev A design
Predecessor: A $ $
D Pay of ASIC NRE
Predecessor: A $ $
E Prep for st proto build boards
Predecessor: C $
b What comments can you make about this project, based on a budget of $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock