Question: 6) A small software development project has eight major activities. The times are estimated and provided in the table below: (10 points) Activity Optimistic Time

6) A small software development project has eight major activities. The times are estimated and provided in the table below: (10 points)

Activity

Optimistic

Time

Most

Likely Time

Pessimistic

Time

Immediate

Predecessor(s)

A

3

4

5

--

B

5

7

9

--

C

2

3

10

A

D

2

5

8

B

E

1

7

7

B

F

3

5

7

C, D

G

7

8

9

D, E

H

2

6

10

F

Answer the following questions based on above table 1-2 (show your work to get full credit):

  1. Draw the network for all activities for software development. Also, Determine ES, EF, LS, LF, and slack for each activity (complete the network for all activities).
  2. Determine the total project completion time and the critical path for software development. What is the project variance?
  3. What is the probability that software development project will finish in 24 weeks or less?

Please show all work!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!