Question: 6) A small software development project has eight major activities. The times are estimated and provided in the table below: (10 points) Activity Optimistic Time
6) A small software development project has eight major activities. The times are estimated and provided in the table below: (10 points)
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time | Immediate Predecessor(s) |
| A | 3 | 4 | 5 | -- |
| B | 5 | 7 | 9 | -- |
| C | 2 | 3 | 10 | A |
| D | 2 | 5 | 8 | B |
| E | 1 | 7 | 7 | B |
| F | 3 | 5 | 7 | C, D |
| G | 7 | 8 | 9 | D, E |
| H | 2 | 6 | 10 | F |
Answer the following questions based on above table 1-2 (show your work to get full credit):
- Draw the network for all activities for software development. Also, Determine ES, EF, LS, LF, and slack for each activity (complete the network for all activities).
- Determine the total project completion time and the critical path for software development. What is the project variance?
- What is the probability that software development project will finish in 24 weeks or less?
Please show all work!