Question: Case 2 Activity Duration (Days) Dependency A 9 Start B 6 A C 4 B, H D 9 C E 11 D, F F 2

Case 2

Activity

Duration (Days)

Dependency

A

9

Start

B

6

A

C

4

B, H

D

9

C

E

11

D, F

F

2

C, I

G

7

Start

H

9

G

I

8

H

J

3

I

K

1

J

  1. Draw the network diagram.

  1. Determine the critical path(s)

  1. Identify Slack time?