Question: Case 2 Activity Duration (Days) Dependency A 9 Start B 6 A C 4 B, H D 9 C E 11 D, F F 2
Case 2
| Activity | Duration (Days) | Dependency |
| A | 9 | Start |
| B | 6 | A |
| C | 4 | B, H |
| D | 9 | C |
| E | 11 | D, F |
| F | 2 | C, I |
| G | 7 | Start |
| H | 9 | G |
| I | 8 | H |
| J | 3 | I |
| K | 1 | J |
-
Draw the network diagram.
-
Determine the critical path(s)
-
Identify Slack time?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts