Question: Exercise 6 Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the
Exercise 6
- Draw the Network Diagram. Use two-pass method to calculate and show the early and late starts and slack for each activity. Highlight the Critical Path.
- Using the Enumeration Method list all the network paths with length.
| Activity | Duration (days) | Immediate Predecessor |
| A | 2 | - |
| B | 2 | A |
| C | 4 | A |
| D | 1 | B |
| E | 3 | C,D |
| F | 2 | C,D |
| G | 4 | E |
| H | 5 | F,G |