Question: Case Study : A Not - for - profit Medical Research Center CASE QUESTIONS 1 . Develop an estimated duration for each activity. 2 .

Case Study : A Not-for-profit Medical Research Center
CASE QUESTIONS 1. Develop an estimated duration for each activity.
2. Using a project start time of 0(or May 15) and a required project completion time of 180 days (or November 15), calculate the ES, EF, LS, and LF times and TS for each activity. If your calculations result in a project schedule with negative TS, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an acceptable baseline schedule for completing the project within 180 days (or by November 15). Describe the revisions you made.
3. Determine the critical path, and identify the activities that make up the critical path.
4. Produce a bar chart (Gantt chart) based on the ES and EF times from the schedule in item 2.
Case Study : The Wedding
1. Develop an estimated duration for each activity.
2. Using a project start time of 0(or January 1) and a required project com-pletion time of 180 days (or June 30), calculate the ES, EF, LS, and LF times and TS for each activity. If your calculations result in a project schedule with negative TS, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an accept-able baseline schedule for completing the project within 180 days (or by June 30). Describe the revisions you made.
3. Determine the critical path, and identify the activities that make up the crit-ical path.
4. Produce a bar chart (Gantt chart) based on the ES and EF times from the schedule in item 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!