Question: Case Study: Construction Craig Construction: Home Improvement Project Having completed the quality planning of the project, Nash wanted to set the expectations of schedule performance

Case Study: Construction Craig Construction: Home Improvement Project

Having completed the quality planning of the project, Nash wanted to set the expectations of schedule performance with Craig. He asked Craig, "What is the order in which you are planning to do the job?"

Craig answered, "Let's see?.?.?.?I will write down the activities for you."

Nash asked Craig to let him know the order in which the activities had to be completed. Craig took out paper and started writing down the activities with their durations. He wrote which of the activities would take precedence over the others.

Nash looked at the list and asked Craig, "So the only activities that can be done at the same time are the window installation and the roof and skylight installation?"

Case Study: Construction Craig Construction: Home Improvement ProjectHaving completed the quality planning

Table 8-7 Project Schedule Activity Description Duration (Days) Site preparation Event Predecessor 2 B Install posts 2 C A Build base and frame 4 D B Install roof and skylights C F Install windows C F Install siding N D G Interior wood work E. F H Lighting and HVAC 3 G Interior dry wall 3 H Painting 1.5 K Flooring 1.5 Cleanup K Craig replied, "Yes." Nash entered all this information into Microsoft Project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!