Question: Case Study D: Free Choice Project Management Company Project Completion (Cont. from case study A, B and C) Below are the notes taken during the

Case Study D: Free Choice Project Management Company Project Completion (Cont. from case study A, B and C)

Below are the notes taken during the project to create a greener space outside of the organisations buildings. The project is now complete, and you have been asked to provide a basic financial report.

As a reminder, initial estimations totalled $27,970 and the organisation allowed $30,000 as the budget.

  • Concrete removal:
  • specialist company successfully broke up existing concrete within the estimated timeframe, cost $6,500 as agreed
  • removal company underestimated the amount of concrete to be removed and required an extra day with another available lorry, extra $600 ($4,000 total)
  • signage and safety issues implemented according to legislation; noise kept to a minimum during work hours
  • all signage required cost $100 ($155 estimated)
  • colleagues volunteered time to help lorries access the area
  • Turf/lawn:
  • 50m turf ($1,750) and 50m topsoil/labour ($750) as agreed
  • turf labour increased by three days due to bad weather, budgeted $900 (actual cost $1,350)
  • Planting:
  • plant order (465 plants) large enough to warrant discount, budgeted $3,325 (actual cost $3,000)
  • planting company needed four days to complete project (budgeted $750, cost $600)
  • sprinkler system, installation and connection totalled $680 (as budgeted)
  • new costing required for ongoing utility charges (water, $65 extra per month)
  • Paving:
  • 30m paving purchased ($1,260) and 5m not required (return value $210)
  • paving specialist company required for four days ($880 as agreed)
  • Shaded area:
  • changed material as recommended by specialist, new cost is $20 per m (20m)
  • 6 x wooden posts ($35 each)
  • shading installation required further digging work, new cost $350 (estimated $290)
  • shading fixings came in at $255 (estimated $135)
  • 3 x benches ($1,000), 20 x chairs ($3,500), 5 x tables ($1,500) budgeted $5,500
  • Other:
  • project manager worked extra 10 hours over the agreed 25 ($45 per hour).

Question 1:

Using the information provided in case study D, complete a financial report by using the following template:

Guideline: the learner is provided example answer in the orange letters at below table

Project Phase Budgeted Cost Actual Cost Comments
Concrete removal $9,900 $10,500 Removal company required extra day
Turf/lawn
Planting
Paving
Shaded area
Other

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!