Question: Case Study D: Free Choice Project Management Company Project Completion (Cont. from case study A, B and C) Below are the notes taken during the
Case Study D: Free Choice Project Management Company Project Completion (Cont. from case study A, B and C)
Below are the notes taken during the project to create a greener space outside of the organisations buildings. The project is now complete, and you have been asked to provide a basic financial report.
As a reminder, initial estimations totalled $27,970 and the organisation allowed $30,000 as the budget.
- Concrete removal:
- specialist company successfully broke up existing concrete within the estimated timeframe, cost $6,500 as agreed
- removal company underestimated the amount of concrete to be removed and required an extra day with another available lorry, extra $600 ($4,000 total)
- signage and safety issues implemented according to legislation; noise kept to a minimum during work hours
- all signage required cost $100 ($155 estimated)
- colleagues volunteered time to help lorries access the area
- Turf/lawn:
- 50m turf ($1,750) and 50m topsoil/labour ($750) as agreed
- turf labour increased by three days due to bad weather, budgeted $900 (actual cost $1,350)
- Planting:
- plant order (465 plants) large enough to warrant discount, budgeted $3,325 (actual cost $3,000)
- planting company needed four days to complete project (budgeted $750, cost $600)
- sprinkler system, installation and connection totalled $680 (as budgeted)
- new costing required for ongoing utility charges (water, $65 extra per month)
- Paving:
- 30m paving purchased ($1,260) and 5m not required (return value $210)
- paving specialist company required for four days ($880 as agreed)
- Shaded area:
- changed material as recommended by specialist, new cost is $20 per m (20m)
- 6 x wooden posts ($35 each)
- shading installation required further digging work, new cost $350 (estimated $290)
- shading fixings came in at $255 (estimated $135)
- 3 x benches ($1,000), 20 x chairs ($3,500), 5 x tables ($1,500) budgeted $5,500
- Other:
- project manager worked extra 10 hours over the agreed 25 ($45 per hour).
Question 1:
Using the information provided in case study D, complete a financial report by using the following template:
Guideline: the learner is provided example answer in the orange letters at below table
| Project Phase | Budgeted Cost | Actual Cost | Comments |
| Concrete removal | $9,900 | $10,500 | Removal company required extra day |
| Turf/lawn | |||
| Planting | |||
| Paving | |||
| Shaded area | |||
| Other |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
