Question: Case Study D: Free Choice Project Management Company Project Completion (Cont. from case study A, B and C) Below are the notes taken during the
Case Study D: Free Choice Project Management Company Project Completion (Cont. from case study A, B and C)
Below are the notes taken during the project to create a greener space outside of the organizations buildings. The project is now complete, and you have been asked to provide a basic financial report.
As a reminder, initial estimations totaled $27,970, and the organization allowed $30,000 as the budget.
Concrete removal:
specialist company successfully broke up existing concrete within the estimated timeframe, cost $6,500 as agreed
removal company underestimated the amount of concrete to be removed and required an extra day with another available lorry, extra $600 ($4,000 total)
signage and safety issues implemented according to legislation; noise kept to a minimum during work hours
all signage required cost $100 ($155 estimated)
colleagues volunteered time to help lorries access the area
Turf/lawn:
50m turf ($1,750) and 50m topsoil/labour ($750) as agreed
turf labour increased by three days due to bad weather, budgeted $900 (actual cost $1,350)
Planting:
plant order (465 plants) large enough to warrant discount, budgeted $3,325 (actual cost $3,000)
planting company needed four days to complete project (budgeted $750, cost $600)
sprinkler system, installation and connection totalled $680 (as budgeted)
new costing required for ongoing utility charges (water, $65 extra per month)
Paving:
30m paving purchased ($1,260) and 5m not required (return value $210)
paving specialist company required for four days ($880 as agreed)
Shaded area:
changed material as recommended by specialist, new cost is $20 per m (20m)
6 x wooden posts ($35 each)
shading installation required further digging work, new cost $350 (estimated $290)
shading fixings came in at $255 (estimated $135)
3 x benches ($1,000), 20 x chairs ($3,500), 5 x tables ($1,500) budgeted $5,500
Other:
project manager worked extra 10 hours over the agreed 25 ($45 per hour).
USING THE CASE STUDY ABOVE PLEASE ANSWER ONLY THIS QUESTION.
Question 1:
Using the information provided in case study D, complete a financial report by using the following template:
Guideline: the learner is provided an example answer in the orange letters below table
| Project Phase | Budgeted Cost | Actual Cost | Comments |
| Concrete removal | $9,900 | $10,500 | Removal company required extra day |
| Turf/lawn |
|
|
|
| Planting |
|
|
|
| Paving |
|
|
|
| Shaded area |
|
|
|
| Other |
|
|
|