Question: Case Study - New Warehouse Design and Construction for Food Manufacturer The Scenario Britain s biggest food manufacturer wanted a centre for warehousing best practice

Case Study - New Warehouse Design and Construction for Food
Manufacturer
The Scenario
Britains biggest food manufacturer wanted a centre for warehousing best practice at one of their 60 UK
sites. The site was set up as a benchmark within the company for the definition and delivery of the
highest possible standards of working practice. The client wished to consolidate its distribution and
warehousing network to cost effectively accommodate past and future acquisitions of competitors.
A building project had already been started without the necessary project management rigour and
controls and WBS were asked first to bring the actual building work under control and secondly to
implement a complete pallet racking and operational infrastructure.
In order to maximise operational efficiency and achieve compliance with current health and safety
regulations WBS were also tasked with a complete redesign and refurbishment of existing warehouses.
This included a drive for best practice and training of all staff working at the distribution centre.
As a consequence of the expansion and refurbishment stock needed to be transferred between several
internal and third party warehouses in order to achieve the most cost effective stock and customer mix.
The Programme
A series of specific projects were identified for the programme:
Build a new 20,000 m2 warehouse
Design and build 16,500 pallet locations to suit current and future product mix
Design and build office and staff amenities block inside the new warehouse
Design and install a pallet conveyor system
Refurbish 15 existing warehouses for health and safety and space optimisation
Create operator and supervisor work instructions for the end-to-end operation
Train 180 staff on all work instructions
Transfer product between client and third party warehouses
The Mechanism
Making changes that lead to sustainable improvements requires a consultative approach involving
everyone affected by the process, in every area of the organisation.
To achieve this deep level of effective change, WBS creates an implementation team made up of WBS
consultants, and representatives from the clients own people. In this instance the client provided two
permanent members to the project team to ensure operational requirements and expertise were always
kept in focus.
A schedule of weekly programme update meetings with all client stakeholders was rigorously adhered to ensuring the right levels of communication and decision
making.
Furthermore, a schedule of weekly contractors meetings was also maintained in order to ensure that all trades were working together and that all issues could be
raised and resolved.
The permanent members of the programme team were each responsible for one or more projects and would draw on relevant people from the clients
organisation to participate in design workshops etc.
The Benefits
Service level improvement from 95% to 98-99% sustained during peak periods
Total cost saving 1.7M
Storage capacity increased by 16,500 pallets from 26.5K to 43K pallets
Warehouse network reduced by 3 warehouses
Modern and safe office and staff facilities
Reduced handling by introducing a pallet conveyor system
Improved layout, flow and pick face design
Lux levels raised from 30 to 250
Brighter and cleaner working environment
5/24/2019 Case Study - New Warehouse Design and Construction for Food Manufacturer
www.wbsgroup.com/Track-Record/Case-Studies/case-study-new-warehouse-design-and-construction-for-food-manufacturer 2/2
7 operators trained as in-house trainers
Created 9 operator and 8 supervisor work instructions
Trained 180 people on work instructions
The Next Steps
WBS were retained to programme manage the further extension of the distribution centre with another 20K+ m2 warehouse including the refurbishment of the
remaining old warehouses on the site.
The new programme also included refurbishment of the yard and the introduction of yard management.
A cost saving of 2.5M by discontinuing a 3rd party warehouse contract was achieved due to the fact that the building project was delivered 3 weeks ahead of an
already extremely tight schedule.Questions for Case Assignment # 3
New Warehouse Design and Construction
Q1: Considering this case, what are some of key mechanism adopted by WMS to ensure that Construction is in line with company expectations?
Q2: Identify 5 key benefits achieved by WBS while taking care of this project?
Q3: What is one key item in this project that ensured successful implementation by WMS group?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!