Question: CASE STUDY Should Packing Be Postponed to the DC ? Penang Electronics ( PE ) is a contract manufacturer that produces and packages private -

CASE STUDY
Should Packing Be Postponed to the DC?
Penang Electronics (PE) is a contract manufacturer that
produces and packages private-label products for several
retail chains, including Target, Best Buy, Staples, and
Office Max. In each case, the basic products are identi-
cal, with the only difference being the labeling and the
packaging. Thus, the labeled and packed version of the
product destined for Target cannot be sent to Best Buy.
Currently, a production facility in Malaysia is used
to manufacture, label, and pack all products. The manu-
facturing facility replenishes a DC in St. Louis, from
which the contract manufacturer fills all customer
orders. The manufacturing and transportation lead time
from Penang to St. Louis is nine weeks. PE uses a con-
tinuous review policy to manage inventories at its DC
and aims to provide a cycle service level of 95 percent
for each product to every customer.
The previous month had been very challenging
because Best Buy requested 5,000 additional units
beyond what was available at the DC, whereas Target
ordered 3,500 fewer units and Staples ordered 4,000
fewer units. Even though there was sufficient product
inventory available at the DC (in the form of the basic
product), PE could not meet the Best Buy request because
the excess inventory available was labeled and packed for
other customers. The DC had leftover inventory from
Target and Staples, which unfortunately could not be
used to serve Best Buy. PE had lost business and surplus
inventory all because of the wrong labels and packaging.
Labeling and Packaging at the DC
The vice president of supply chain at PE proposed post-
poning the final labeling and packaging to the DC. Her
logic was that postponing labeling and packaging to the
DC would allow PE to use all available inventories to serve
any customer. In particular, the situation that arose in the
previous month when Best Buy did not get its entire order
could have been avoided through postponement. If packag-
ing was shifted to the DC, the lead time of manufacturing
and transporting the basic product from Malaysia would
continue to be about nine weeks. Labeling and packaging
were relatively quick steps and the response time from the
DC to the customer was not expected to change.
The DC management was opposed to this idea
because it would add additional work that was different
from what they had done so far. A detailed study of the
production process had shown that labeling and packag-
ing at the DC cost $2 per unit more than the cost of label-
ing and packaging in Malaysia. DC management believed
that this increase in cost would be held against them once
the process was changed, and they would be under con-
stant pressure to lower cost. They also believed it would
complicate the work they did when filling an order and
could adversely impact customer service.
Evaluating the Two Options
To evaluate the two options, a team from both manufactur-
ing and the DC was set up. The team decided to focus its
analysis on three major product categories-computers,
printers, and scanners, and four major customers-Target,
Best Buy, Staples, and Office Max. Weekly demand for
each product and customer is shown in Table 12-9. In each
case, "Mean" indicates the average weekly demand, and
"SD" indicates the standard deviation of weekly demand.
All demand was assumed to be normally distributed. PE
incurred a total cost of $1,000 per computer, $300 per
printer, and $100 per scanner. Given the short life cycle of
these products, PE used a holding cost of 30 percent when
making its inventory decisions. The team analyzed the
impact of postponement on safety inventories before mak-
ing a final recommendation.
Questions
What is the annual inventory cost of the current system in
which product is produced, labeled, and packed in Malay-
sia before being shipped to the DC?
How would the inventory cost change if labeling and pack-
aging were moved to the DC? Evaluate the change in
inventory costs as the correlation coefficient of demand
between any pair of customers varies from 0 to 0.5 to 1.0.
How should PE set up its production, labeling, and pack-
aging processes? Does your answer change if the addi-
tional cost of labeling and packaging at the DC is reduced
to $1(from the current value of $2)?
 CASE STUDY Should Packing Be Postponed to the DC? Penang Electronics

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!