Question: CASE STUDY Should Packing Be Postponed to the DC? Penang Electronics (PE) is a contract manufacturer that produces and packages private-label products for several
CASE STUDY Should Packing Be Postponed to the DC? Penang Electronics (PE) is a contract manufacturer that produces and packages private-label products for several retail chains, including Target, Best Buy, Staples, and Office Max. In each case, the basic products are identi- cal, with the only difference being the labeling and the packaging. Thus, the labeled and packed version of the product destined for Target cannot be sent to Best Buy. Currently, a production facility in Malaysia is used to manufacture, label, and pack all products. The manu- facturing facility replenishes a DC in St. Louis, from which the contract manufacturer fills all customer orders. The manufacturing and transportation lead time from Penang to St. Louis is nine weeks. PE uses a con- tinuous review policy to manage inventories at its DC and aims to provide a cycle service level of 95 percent for each product to every customer. The previous month had been very challenging because Best Buy requested 5,000 additional units beyond what was available at the DC, whereas Target ordered 3,500 fewer units and Staples ordered 4,000 fewer units. Even though there was sufficient product inventory available at the DC (in the form of the basic product), PE could not meet the Best Buy request because the excess inventory available was labeled and packed for other customers. The DC had leftover inventory from Target and Staples, which unfortunately could not be used to serve Best Buy. PE had lost business and surplus inventory all because of the wrong labels and packaging. Labeling and Packaging at the DC The vice president of supply chain at PE proposed post- poning the final labeling and packaging to the DC. Her logic was that postponing labeling and packaging to the DC would allow PE to use all available inventories to serve any customer. In particular, the situation that arose in the previous month when Best Buy did not get its entire order could have been avoided through postponement. If packag- ing was shifted to the DC, the lead time of manufacturing and transporting the basic product from Malaysia would continue to be about nine weeks. Labeling and packaging were relatively quick steps and the response time from the DC to the customer was not expected to change. The DC management was opposed to this idea because it would add additional work that was different from what they had done so far. A detailed study of the production process had shown that labeling and packag- ing at the DC cost $2 per unit more than the cost of label- ing and packaging in Malaysia. DC management believed that this increase in cost would be held against them once the process was changed, and they would be under con- stant pressure to lower cost. They also believed it would complicate the work they did when filling an order and could adversely impact customer service. Evaluating the Two Options To evaluate the two options, a team from both manufactur- ing and the DC was set up. The team decided to focus its analysis on three major product categoriescomputers. printers, and scanners, and four major customers-Target, Best Buy, Staples, and Office Max. Weekly demand for each product and customer is shown in Table 12-9. In each case, "Mean" indicates the average weekly demand, and "SD" indicates the standard deviation of weekly demand. All demand was assumed to be normally distributed. PE incurred a total cost of $1,000 per computer, $300 per printer, and $100 per scanner. Given the short life cycle of these products, PE used a holding cost of 30 percent when making its inventory decisions. The team analyzed the impact of postponement on safety inventories before mak- ing a final recommendation. TABLE 12-9 Distribution of Weekly Demand by Product and Customer Computers Printers Scanners Mean SD Mean SD Mean SD Target 1,000 700 2,000 1,000 4,000 1,000 Best Buy 700 600 1,500 800 4,500 900 Office Max 800 600 1,200 600 2,000 700 Staples 500 400 900 500 1,400 500
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
