Question: Case Study : The Wedding Using a project start time of 0 (or January 1) and a required project com-pletion time of 180 days (or
Case Study : The Wedding
Using a project start time of 0 (or January 1) and a required project com-pletion time of 180 days (or June 30), calculate the ES, EF, LS, and LF times and TS for each activity. If your calculations result in a project schedule with negative TS, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an accept-able baseline schedule for completing the project within 180 days (or by June 30). Describe the revisions you made.