Question: CcDdEe bCcDdEe List Para... Normal bCcDdEe cDdEe Cc I No Spaci... Heading 1 He Styles Activity Immediate predecessors Activity time () 4 3 B D
CcDdEe bCcDdEe List Para... Normal bCcDdEe cDdEe Cc I No Spaci... Heading 1 He Styles Activity Immediate predecessors Activity time () 4 3 B D E F G H A D B B G F HI HI JK 1 4 5 J 1 K 1 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity CcDdEe bCcDdEe List Para... Normal bCcDdEe cDdEe Cc I No Spaci... Heading 1 He Styles Activity Immediate predecessors Activity time () 4 3 B D E F G H A D B B G F HI HI JK 1 4 5 J 1 K 1 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity