Question: CCPM Assignment Please answer Task Duration Hidden buffer Immediate Predecessor Resource 1 A 8 4 Nil John 2 B 20 10 Nil Tom 3 C
CCPM Assignment
Please answer
| Task | Duration | Hidden buffer | Immediate Predecessor | Resource | |
| 1 | A | 8 | 4 | Nil | John |
| 2 | B | 20 | 10 | Nil | Tom |
| 3 | C | 10 | 5 | Nil | Drick |
| 4 | D | 12 | 6 | 1 | Harry |
| 5 | E | 10 | 5 | 3 | Drick |
| 6 | F | 4 | 2 | 2,3 | Tom |
| 7 | G | 2 | 1 | 6 | Drick |
| 8 | H | 6 | 3 | 4, 6 | Harry |
| 9 | I | 18 | 9 | 5, 6, 11 | Drick |
| 10 | J | 14 | 7 | 7, 8 | Tom |
| 11 | K | 24 | 12 | Nil | David |
| 12 | L | 6 | 3 | 11 | John |
| 13 | M | 8 | 4 | 9, 10, 12 | Harry |
Assume that there is a 50% hidden buffer in each activity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock