Question: CD) A project being analyzed by PERT/CPM has 35 activities. 11 of which are on the critical path of the estimated time on the path

CD) A project being analyzed by PERT/CPM has 35
CD) A project being analyzed by PERT/CPM has 35 activities. 11 of which are on the critical path of the estimated time on the path is 108 days and the variance is 49, the probability that the project will be completed in 101 days approximate samal Select one a. 0,841 eb. 0,263 c. 0.023 d. 0.341 e e. 0.159 P. M