Question: A project being analyzed by PERT has 3 0 activities, 1 1 of which are on the critical path. If the estimated time along the

A project being analyzed by PERT has 30 activities, 11 of which are on the critical path. If the estimated time along the critical path is 215 days with a project variance of 100, what is the probability that the project will take 225 days or more to complete?
A) Near zero
B)0.13
C)0.16
(D)0.84
E)1.70
 A project being analyzed by PERT has 30 activities, 11 of