Question: Celify :GE - - 5 1 0 3 - 2 D 1 - SP - 2 0 2 3 [ Based on Project Management Professional
Celify :GEDSPBased on Project Management Professional PMP Based on PMBOK
D When calculating the schedule variance of a project that is around percent complete, which formula would you use?
Earned value divided by the actual cost
B
Earned value minus the planned value
C
Earned value minus the actual cost
Earned value divided by the planned value