A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone.
To reduce the risk with this approach, which step should the business analyst take?
Ask the stakeholders in the elicitation sessions to speak on behalf of stakeholders in other time zones.
Add the risk to the risk register so other stakeholders are aware of the approach.
Request the project sponsor to approve this requirements elicitation approach for this project.
Distribute the documented requirements to relevant stakeholders in all time zones for review and comment.
Previous
savigator
Nerit?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock