Question: Certified Associate in Project Management Time Remaining 1 4 4 : 1 7 E Comment Highlight ( J ) Strikethrough ( W ) $ 3

Certified Associate in Project Management
Time Remaining 144:17
E Comment Highlight (J) Strikethrough (W)
$
33 of 150
Flag for Review
An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.
Which of the following changes has caused this loss in productivity?
The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.
Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.
Two of the team members have been working in silos using different methods to validate their performance.
The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.
Previous
%idavigator
Next =>
 Certified Associate in Project Management Time Remaining 144:17 E Comment Highlight

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!