Question: Ch . 1 1 : Aggregate Planning and Master Scheduling _ MPS _ Plessey Pumps ( 5 Pts ) Plessey Pumps manufactures a line of

Ch.11: Aggregate Planning and Master Scheduling_MPS_Plessey Pumps (5 Pts)
Plessey Pumps manufactures a line of Industrial Pumps. Information for one of their pumps, part number A-13.16, is presented below.
Forecast for sales: 50 per week in each of weeks 1-8
Lot Sizing: Multiples of 75 pieces
Firm customer sales order:
Week 1: 52
Week 2: 35
Week 3: 20
Week 4: 12.
a). Prepare the Master Production Schedule for part number A-1316, using the template below.
Master Production Schedule for PN A-1316
\begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|}
\hline \begin{tabular}{l}
Beg Inv. \(=\)\\
SS=\\
Lot Sizing:
\end{tabular} & \multicolumn{6}{|l|}{ Week or Period }\\
\hline & PD & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & \\
\hline Forecast & & & & & & & & & & \\
\hline Customer Orders & & & & & & & & & & \\
\hline Gross Requirements & & & & & & & & & \\
\hline Existing MPS Quantities & & & & & & & & & \\
\hline Projected On Hand & & & & & & & & & \\
\hline Net Requirements & & & & & & & & & & \\
\hline Planned MPS Receipts & & & & & & & & & & \\
\hline Planned MPS Releases & & & & & & & & & & \\
\hline Available-to-Promise & & & & & & & & & & \\
\hline
\end{tabular}
Ch 11_Aggregate Planning and Master Scheduling_MPS_Plessey_Pumps Ch.11: Aggregate Planning and Master Scheduling_MPS_Plessey Pumps (5 Pts)
Plessey Pumps manufactures a line of Industrial Pumps. Information for one of their pumps, part number A-13.16, is presented below.
Forecast for sales: 50 per week in each of weeks 1-8
Lot Sizing: Multiples of 75 pieces
Firm customer sales order:
Week 1: 52
Week 2: 35
Week 3: 20
Week 4: 12.
a). Prepare the Master Production Schedule for part number A-1316, using the template below.
Master Production Schedule for PN A-1316
\begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|}
\hline \begin{tabular}{l}
Beg Inv. \(=\)\\
SS=\\
Lot Sizing:
\end{tabular} & \multicolumn{6}{|l|}{ Week or Period }\\
\hline & PD & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & \\
\hline Forecast & & & & & & & & & & \\
\hline Customer Orders & & & & & & & & & & \\
\hline Gross Requirements & & & & & & & & & \\
\hline Existing MPS Quantities & & & & & & & & & \\
\hline Projected On Hand & & & & & & & & & \\
\hline Net Requirements & & & & & & & & & & \\
\hline Planned MPS Receipts & & & & & & & & & & \\
\hline Planned MPS Releases & & & & & & & & & & \\
\hline Available-to-Promise & & & & & & & & & & \\
\hline
\end{tabular}
Ch 11_Aggregate Planning and Master Scheduling_MPS_Plessey_Pumps Ch.11: Aggregate Planning and Master Scheduling_MPS_Plessey Pumps (5 Pts)
Plessey Pumps manufactures a line of Industrial Pumps. Information for one of their pumps, part number A-13.16, is presented below.
Forecast for sales: 50 per week in each of weeks 1-8
Lot Sizing: Multiples of 75 pieces
Firm customer sales order:
Week 1: 52
Week 2: 35
Week 3: 20
Week 4: 12.
a). Prepare the Master Production Schedule for part number A-1316, using the template below.
Master Production Schedule for PN A-1316
\begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|}
\hline \begin{tabular}{l}
Beg Inv. \(=\)\\
SS=\\
Lot Sizing:
\end{tabular} & \multicolumn{6}{|l|}{ Week or Period }\\
\hline & PD & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & \\
\hline Forecast & & & & & & & & & & \\
\hline Customer Orders & & & & & & & & & & \\
\hline Gross Requirements & & & & & & & & & \\
\hline Existing MPS Quantities & & & & & & & & & \\
\hline Projected On Hand & & & & & & & & & \\
\hline Net Requirements & & & & & & & & & & \\
\hline Planned MPS Receipts & & & & & & & & & & \\
\hline Planned MPS Releases & & & & & & & & & & \\
\hline Available-to-Promise & & & & & & & & & & \\
\hline
\end{tabular}
Ch 11_Aggregate Planning and Master Scheduling_MPS_Plessey_Pumps
Ch . 1 1 : Aggregate Planning and Master

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!