Question: Ch . 1 1 : Aggregate Planning and Master Scheduling _ MPS _ Plessey Pumps ( 5 Pts ) Plessey Pumps manufactures a line of
Ch: Aggregate Planning and Master SchedulingMPSPlessey Pumps Pts
Plessey Pumps manufactures a line of Industrial Pumps. Information for one of their pumps, part number A is presented below.
Forecast for sales: per week in each of weeks
Lot Sizing: Multiples of pieces
Firm customer sales order:
Week :
Week :
Week :
Week :
a Prepare the Master Production Schedule for part number A using the template below.
Master Production Schedule for PN A
tabletableBeg Inv. SS Lot Sizing:Week or PeriodPDForecastCustomer OrdersGross RequirementsExisting MPS QuantitiesProjected On HandNet RequirementsPlanned MPS ReceiptsPlanned MPS ReleasesAvailabletoPromise,,,,,,,,,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock