Question: (CH5) It's important for you, the project manager, to understand what each of the project management processes creates. One of the key processes you'll do

(CH5) It's important for you, the project

(CH5) It's important for you, the project manager, to understand what each of the project management processes creates. One of the key processes you'll do is scope control throughout your project. Which of the following is an output of scope control? a. Work-around b. Change request for a corrective action c. Transference O d. Risk assessment