Question: Ch9: - Answer the questions for the below network: Activity T.F. Crashed Duration 5 9 15 Slope Cost 100 60 60 5 Normal Duration 8

Ch9: - Answer the questions for the below
Ch9: - Answer the questions for the below network: Activity T.F. Crashed Duration 5 9 15 Slope Cost 100 60 60 5 Normal Duration 8 12 3 6 6 12 0-6 0 o 1 12. 4-10 40 3 4 10 6 15 15 11 10 0 15 20 75 6-10 6-12 6-8 2-8 10-12 8-12 14 200 5 3 3 Normal Situation 0 a) What is the minimum time to complete the project above? b) What is the minimum cost to complete the project in minimum time? c) What is the minimum cost to complete the project in 22 days