Question: CHaD has recalculated their project scheduling information to include uncertainty into the activity times as indicated below: Activity ID a m b t v Design
CHaD has recalculated their project scheduling information to include uncertainty into the activity times as indicated below:
| Activity | ID | a | m | b | t | v |
| Design Laptop | A | 10 | 22 | 28 |
|
|
| Build Prototype | B | 4 | 6 | 14 |
|
|
| Evaluate Design | C | 4 | 4 | 10 |
|
|
| Test Prototype | D | 1 | 2 | 3 |
|
|
| Write Manual | E | 7 | 8 | 9 |
|
|
| Prep Production | F | 1 | 5 | 9 |
|
|
| Test Production | G | 2 | 2 | 2 |
|
|
Determine the critical path:
| ID | ES | EF | LS | LF | TS | CP |
| A |
|
|
|
|
|
|
| B |
|
|
|
|
|
|
| C |
|
|
|
|
|
|
| D |
|
|
|
|
|
|
| E |
|
|
|
|
|
|
| F |
|
|
|
|
|
|
| G |
|
|
|
|
|
|
What is the probability the project is completed in 44 weeks or less?
What is the probability the project is completed in 38 weeks or less?